Worship Area Renovation Project – Information Meeting Q&A:
Why is the sanctuary being renovated first?
The sanctuary is the most sacred and visible part of our church, where the Holy Sacrifice of the Mass is offered. Over time, the steps have become permanently stained, and the elevation changes are difficult to discern. Phase I of the renovation will restore the beauty and clarity of the sanctuary, reflecting the reverence due to this sacred space.
Why not wait until all funds are secured and complete the entire project at once?
By beginning with the sanctuary, which is fully funded, we hope to inspire a deeper appreciation for the beauty and reverence of our worship space. True beauty, which comes from God, elevates our hearts and minds to Him. A sacred space that reflects divine beauty invites prayer and contemplation, drawing us into a deeper communion with the Lord. Our hope would be to fund Phase II as soon as we can.
Is the design finalized?
Yes, the design is complete and final.
Will the grit on the floor wear down? Will the finish need to be reapplied?
Yes, the specialized finish, which enhances traction while ensuring ease of maintenance, will need periodic reapplication. Given the light use of this flooring, the exact timeline for reapplication is uncertain, but it will involve stripping and refinishing the surface as needed. This will be done by our maintenance team.
Where are the prayer intentions placed in the floor?
There was a small compartment in the floor, where all prayer intentions that were collected could be reverently sealed within the sacred space. It has been marked with a brass cross, and is located in front of the altar.
Will a handicap ramp be installed for access to the sanctuary?
Due to spatial limitations, a handicap ramp to the sanctuary is not feasible. However, the sanctuary remains accessible in accordance with the requirements of the worship area. New beautiful railings will be installed on the steps of the Sanctuary. Please refer to the design.
Are the renovation funds in an interest-bearing account?
Yes, all funds for the project are currently held in a money market account, earning an investment return of 4%+.
If we wait two years to secure funding for Phase II, will the total cost change?
Yes, the projected cost of Phase II will fluctuate due to inflation and changes in material and labor expenses. Estimated funding for Phase II is $150,000. Currently, we have received $23,000.